Batangas LNG Terminal

Customer: First Gen

Contract: EPC

Location: Batangas, Philippines

Ports & Coastal Solutions South East Asia

Fast Facts

  • New multi-purpose jetty with topside infrastructure
  • Onshore facilities, including the control room
  • 24-inch, 1.3 km long high-pressure gas pipeline
  • Extensive earthworks, including tsunami bund wall and access road

FGEN LNG Corporation (FGEN) engaged us to build and deliver the Interim Offshore Terminal Project ("IOT Project") at their LNG terminal in Batangas, in the Philippines.

We undertook the engineering, procurement, and construction of both the Multi-Purpose Jetty and Onshore Gas Receiving Facility. The new Multiple Purpose Jetty is a permanent modification of the existing liquid fuel jetty which we constructed in 1998.

Now complete, the IOT Project accelerated the introduction of LNG into the country and serves the natural gas requirements of existing and future gas-fired power plants in the Philippines.

The IOT Project was an energy infrastructure project of national significance. It provides many benefits to local communities and has played a critical role in ensuring the energy security of the Luzon Grid and the Philippines.

Project Scope:

The Multi-Purpose Jetty is located adjacent to the existing jetty and is capable of receiving liquid fuel carriers, LNG carriers, FSRUs, and FSUs. The new jetty structures comprise a total of 10,000 MT (212 no) tubular steel piles ranging from 45 – 65 m in length. The superstructure comprises approximately 15,500 MT of fabricated steel jackets and deck/trestle modules. The Loading Platform is topped by a reinforced concrete deck slab which accommodates 2 ship gangways, 3 HP Gas Unloading Arms, and a jib crane, among its critical deck equipment.

Onshore facilities include a Jetty Monitoring Building and Facilities Control Room founded on piled foundation slabs and incorporating all associated services and civil infrastructure.

A 24” high-pressure gas pipeline approximately 1.3 km in length transports gas from the Loading Platform to the Gas Receiving Facility which comprises a piled metering area and includes 4 metering stations and static mixers. The pipeline is a combination of buried and above-ground pipe found on piled pipe racks and concrete footings along its length.

The civil works included general earthworks, the construction of a tsunami bund wall, and a 2 km of roadway.

Project Gallery