Customer: Petronas Contract: EPCC Location: Tanjung Setapa, Malaysia |
Fast Facts
|
We designed, constructed and commissioned a new jetty and associated handling facilities for Petronas, as part of their RAPID (refinery and petrochemical integrated development) project in Malaysia.
The main element of our scope was a Solid Products Handling Jetty, comprising of a 1300 m long trestle, 710 m long jetty head, two container berths and a sulphur loading berth.
We also delivered topside and landside material handling systems for sulphur, with loaders, unloaders and all associated mechanical and electrical works.
Our onshore civil works comprised of a container stacking yard, truck and trailer parks, a workshop area, roads, and site utilities.
We also constructed industrial buildings comprising a 450m long sulphur stockpile warehouse, a terminal operations building, an administration building, workshop, substations, and other ancillary facilities.
The project duration was 30 months, which included an extensive six months of engineering design.