Māngere Biological Nutrient Removal Facility Upgrade

 

Customer: Watercare 

Contract type:  Construct only 

Location: Auckland, New Zealand 

 

Water & Wastewater Solutions New Zealand & Pacific Islands

Fast Facts

  • 200 staff 
  • 830,000-man hours worked 
  • 120,000 m3 earth moved  
  • 15,500 m3 of concrete poured, or 750 concrete truckloads  
  • 2,400 of 150 mm Universal Column (UC) steel piles weighing 500kg each were installed - covering 42 km 
  • 323 precast concrete panels  
  • 144 km of tensioning cable 

McConnell Dowell, in joint venture with HEB, delivered an additional Biological Nutrient Removal (BNR) facility for Watercare as part of its expansion of processing facilities at Māngere Resource Recovery Facility (MRRF).  

The scope of work involved the construction of two reactors, two clarifiers, a blower building, splitter boxes (including for future duplication of reactors in 10 years), secondary effluent (SEF) pipeline, sludge storage tanks and interconnecting SEF pipework to provide additional secondary treatment capacity of approximately 250,000 people.

We successfully installed the twin SEF pipes using a pipejacking method, which required precision in execution due to a gas main, 33 kV cable, and the main fuel main from the Marsden Point Refinery to Auckland and the airport running along the alignment.  

The challenge 

Working adjacent to critical services and an operational plant in a constrained brownfields environment required stringent safety management. We developed a strong safety culture and implemented a thorough training and awareness programme to ensure all staff understood and proactively mitigated the risks of a high-hazard environment. 

The solution 

Understanding the constraints of working in a brownfield environment was essential to ensuring production targets were achieved. The JV team worked collaboratively with Watercare to enhance the programme and provide alternate solutions that saved Watercare money. 

The JV was responsible for the design and construction of the reactor and clarifier tanks, which are lightweight, post-tensioned precast concrete structures. Underlying soft soils saw these large tanks founded on some 2,400 driven piles. Large precast concrete panels were cast and erected on-site to form the tank walls. This provided an economical, safer construction methodology by reducing the amount of work at height required.

 Ongoing works

Project Gallery