It was an absolute delight to see our team awarded the 'Project Controls Innovation of the Year' at the recent Asia Pacific Project Controls Awards in Melbourne.
The team were selected based on their innovative digital engineering solution for the construction of the Eumemmerring Creek Bridge, part of the Cranbourne Line Upgrade Project delivered by our Western Program Alliance (WPA).
The team created a full "digital rehearsal" of the bridge launch including developing detailed temporary works and construction sequencing. Through this digital approach all potenital construction issues were resolved virtually, well in advance of any works taking place on site. And all of this was done online, with stakeholders collaborating remotely from their homes and locked down worksites.
Congratulations to the all involved.
For more information on the project and to see the bridge launch, click here.