McConnell Dowell working with the vertical building arm of the Group Built Environs, on the development of the Auckland International Airport Limited (AIAL) facilities.
Built Environs was awarded the Enabling Works for the WP2 Western Terminal Project in December 2022 and McConnell Dowell is completing the civil work scope.
The contract is part of the Airport’s infrastructure investment plan to combine the domestic and international terminals and provide for a future shift to mass rapid transit.
The civil work scope includes the relocation of the existing parking areas and the construction of a new trucking route for the western terminal.
General Manager Built Environs New Zealand, Greg Ford says: “This contract builds on other successful projects we have completed together such as the Puhinui Train Station. McConnell Dowell has completed several upgrades at the airport and their relationships, experience working in an operational Airport, and knowledge of AIAL’s systems and processes will be a great advantage for the team. We look forward to ‘working together’ in the spirit of our shared values on this important infrastructure project.
The team began the enabling works in February 2023 and is expected to complete this stage in the middle of the year.
For more information about the project, go to: https://www.mcconnelldowell.com/projects/auckland-international-airport